Substation Scout

Kewaunee, WI interconnection queue

2 active projects totaling 43 MW in the MISO queue, plus 3 with terminal status (shown grayed).

2active projects
43active MW
5total filed
Queue IDProjectkVMWResourceStatus
G570 Not reported n/r 125 Wind Withdrawn
G410 Not reported 138 99 Wind Withdrawn
G165 Not reported n/r 38 Nuclear Operational
G391 Not reported n/r 10 Nuclear Withdrawn
G383 Not reported n/r 5 Nuclear Operational

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with MISO before relying on these figures.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first