Kalamazoo, MI interconnection queue

4 active projects totaling 626.4 MW in the MISO queue, plus 2 with terminal status (shown grayed).

4active projects
626.4active MW
6total filed
Queue IDProjectkVMWResourceStatus
J3537 Not reported 138 265 Battery Withdrawn
J2814 Not reported 138 220 Solar Active
J1894 Not reported 138 200 Battery Active
J2906 Not reported 138 200 Battery Active
J561 Not reported n/r 190 Gas Withdrawn
J571 Not reported 138 6.4 Gas Active

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with MISO before relying on these figures.