Substation Scout

Juneau, WI interconnection queue

3 active projects totaling 445 MW in the MISO queue, plus 4 with terminal status (shown grayed).

3active projects
445active MW
7total filed
Queue IDProjectkVMWResourceStatus
J1502 Not reported 345 225 Solar Active
J3402 Not reported n/r 200 Battery Active
G115 Not reported n/r 100 Other Withdrawn
G114 Not reported n/r 60 Other Withdrawn
J1397 Not reported 69 25 Solar Withdrawn
J1429 Not reported 69 24 Battery Withdrawn
G148 Not reported n/r 20 Gas Operational

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with MISO before relying on these figures.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first