Substation Scout

Jasper, TX interconnection queue

0 active projects totaling 0 MW in the MISO queue, plus 4 with terminal status (shown grayed).

0active projects
0active MW
4total filed
Queue IDProjectkVMWResourceStatus
J3079 Not reported 138 200 Solar Withdrawn
J2103 Not reported n/r 100 Solar Withdrawn
J3425 Not reported n/r 59.2 Solar Withdrawn
J2976 Not reported 138 50 Hybrid Withdrawn

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with MISO before relying on these figures.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first