Fayette, IA interconnection queue

1 active project totaling 36 MW in the MISO queue, plus 7 with terminal status (shown grayed).

1active projects
36active MW
8total filed
Queue IDProjectkVMWResourceStatus
G972 Not reported 345 400 Wind Withdrawn
J410 Not reported 345 300 Wind Withdrawn
G985 Not reported 161 200 Wind Withdrawn
J1467 Not reported 161 150 Wind Withdrawn
J409 Not reported 161 150 Wind Withdrawn
J959 Not reported 161 150 Wind Withdrawn
J1438 Not reported 161 100 Solar Withdrawn
H008 Not reported 69 36 Wind Operational

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with MISO before relying on these figures.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first