Crawford, IA interconnection queue

1 active project totaling 100 MW in the MISO queue, plus 3 with terminal status (shown grayed).

1active projects
100active MW
4total filed
Queue IDProjectkVMWResourceStatus
J896 Not reported 161 150 Wind Withdrawn
R29 Not reported n/r 100.8 Wind Withdrawn
R23 Not reported 161 100 Wind Operational
R25 Not reported 161 50 Wind Withdrawn

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with MISO before relying on these figures.