Columbia, AR interconnection queue
4 active projects totaling 762 MW in the MISO queue, plus 5 with terminal status (shown grayed).
4active projects
762active MW
9total filed
| Queue ID | Project | kV | MW | Resource | Status |
|---|---|---|---|---|---|
| J3131 | Not reported | 115 | 300 | Solar | Active |
| J2923 | Not reported | 115 | 240 | Hybrid | Withdrawn |
| J2924 | Not reported | 345 | 222 | Hybrid | Active |
| J2800 | Not reported | 115 | 200 | Solar | Withdrawn |
| J2681 | Not reported | 115 | 170 | Solar | Withdrawn |
| J3624 | Not reported | 115 | 155 | Solar | Withdrawn |
| J3132 | Not reported | 115 | 150 | Battery | Withdrawn |
| J2901 | Not reported | 115 | 140 | Solar | Active |
| J3917 | Not reported | 115 | 100 | Solar | Active |
A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with MISO before relying on these figures.