Columbia, AR interconnection queue

4 active projects totaling 762 MW in the MISO queue, plus 5 with terminal status (shown grayed).

4active projects
762active MW
9total filed
Queue IDProjectkVMWResourceStatus
J3131 Not reported 115 300 Solar Active
J2923 Not reported 115 240 Hybrid Withdrawn
J2924 Not reported 345 222 Hybrid Active
J2800 Not reported 115 200 Solar Withdrawn
J2681 Not reported 115 170 Solar Withdrawn
J3624 Not reported 115 155 Solar Withdrawn
J3132 Not reported 115 150 Battery Withdrawn
J2901 Not reported 115 140 Solar Active
J3917 Not reported 115 100 Solar Active

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with MISO before relying on these figures.