Clark, WI interconnection queue

1 active project totaling 190 MW in the MISO queue, plus 5 with terminal status (shown grayed).

1active projects
190active MW
6total filed
Queue IDProjectkVMWResourceStatus
J1631 Not reported 345 200 Wind Withdrawn
J2018 Not reported 345 190 Solar Withdrawn
J3204 Not reported 345 190 Wind Active
J1866 Not reported 115 125 Wind Withdrawn
J2014 Not reported 345 100 Battery Withdrawn
J814 Not reported 345 99.9 Wind Withdrawn

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with MISO before relying on these figures.