Chicot, AR interconnection queue

3 active projects totaling 485 MW in the MISO queue, plus 9 with terminal status (shown grayed).

3active projects
485active MW
12total filed
Queue IDProjectkVMWResourceStatus
J3426 Not reported n/r 500 Solar Withdrawn
J2143 Not reported 115 250 Solar Active
J2850 Not reported 230 250 Solar Withdrawn
J2451 Not reported 230 200 Solar Withdrawn
J698 Not reported 115 150 Solar Withdrawn
J2985 Not reported 115 135 Solar Active
J2941 Not reported 115 100 Solar Withdrawn
J620 Not reported 115 100 Solar Operational
J922 Not reported 115 100 Solar Withdrawn
J2644 Not reported 115 90 Solar Withdrawn
J2995 Not reported 115 80 Battery Withdrawn
J350 Not reported 115 50 Solar Withdrawn

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with MISO before relying on these figures.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first