Cass, MI interconnection queue

1 active project totaling 539 MW in the MISO queue, plus 2 with terminal status (shown grayed).

1active projects
539active MW
3total filed
Queue IDProjectkVMWResourceStatus
J4102 Not reported 345 539 Solar Active
J1075 Not reported 345 350 Wind Withdrawn
J1077 Not reported 345 250 Wind Withdrawn

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with MISO before relying on these figures.