Ashley, AR interconnection queue

4 active projects totaling 475 MW in the MISO queue, plus 4 with terminal status (shown grayed).

4active projects
475active MW
8total filed
Queue IDProjectkVMWResourceStatus
J2153 Not reported n/r 200 Hybrid Active
J3613 Not reported 115 180 Solar Withdrawn
J3614 Not reported 115 180 Battery Withdrawn
J680 Not reported 115 100 Solar Active
J904 Not reported 115 100 Solar Withdrawn
J603 Not reported 115 100 Solar Active
J902 Not reported 115 100 Solar Withdrawn
J1281 Not reported 115 75 Solar Active

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with MISO before relying on these figures.