Substation Scout

Ascension Parish, LA interconnection queue

0 active projects totaling 0 MW in the MISO queue, plus 4 with terminal status (shown grayed).

0active projects
0active MW
4total filed
Queue IDProjectkVMWResourceStatus
J1151 Not reported 230 252 Gas Withdrawn
J1685 Not reported 230 250 Hybrid Withdrawn
J1618 Not reported 230 200 Solar Withdrawn
J2839 Not reported 230 200 Solar Withdrawn

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with MISO before relying on these figures.