Adams, WI interconnection queue
1 active project totaling 200 MW in the MISO queue, plus 2 with terminal status (shown grayed).
1active projects
200active MW
3total filed
| Queue ID | Project | kV | MW | Resource | Status |
|---|---|---|---|---|---|
| J2520 | Not reported | 138 | 200 | Solar | Active |
| J1160 | Not reported | 138 | 100.2 | Solar | Withdrawn |
| J2293 | Not reported | n/r | 50 | Hybrid | Withdrawn |
A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with MISO before relying on these figures.