Substation Scout

Adair, MO interconnection queue

3 active projects totaling 700 MW in the MISO queue, plus 2 with terminal status (shown grayed).

3active projects
700active MW
5total filed
Queue IDProjectkVMWResourceStatus
G578 Not reported 161 300 Wind Withdrawn
J3199 Not reported 345 300 Hybrid Active
J598 Not reported 345 300 Wind Withdrawn
J1182 Not reported 345 250 Solar Operational
J2142 Not reported 345 150 Hybrid Active

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with MISO before relying on these figures.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first