Substation Scout

Green River substation on the side substation interconnection queue

0 active projects totaling 0 MW in the LG&E and KU queue, plus 7 with terminal status (shown grayed).

7 LG&E and KU queue filings name Green River substation on the side as the point of interconnection, all in KY.

0active projects
0active MW
7total filed
Queue IDProjectkVMWResourceStatus
LGE-GIS-2013-002 Not reported 161 898 Hybrid Withdrawn
LGE-GIS-2007-001 Not reported 161 750 Gas Withdrawn
LGE-GIS-2009-002 Not reported 161 690 Gas Withdrawn
LGE-GIS-2010-003 Not reported 161 690 Hybrid Withdrawn
LGE-GIS-2007-003 Not reported 161 640 Gas Withdrawn
LGE-GIS-2007-002 Not reported 161 610 Gas Withdrawn
LGE-GIS-2009-003 Not reported 161 560 Hybrid Withdrawn

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with LG&E and KU before relying on these figures.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first