0 active projects
totaling 0 MW in the LG&E and KU queue, plus 5 with terminal status (shown grayed).
0active projects
0active MW
5total filed
Queue ID
Project
kV
MW
Resource
Status
LGE-GIS-2019-006
Not reported
69
200
Solar
Withdrawn
LGE-GIS-2021-002
Not reported
161
150
Solar
Withdrawn
LGE-GIS-2018-004
Not reported
161
120
Solar
Withdrawn
LGE-GIS-2019-013
Not reported
161
100
Solar
Withdrawn
LGE-GIS-2019-019
Not reported
161
100
Solar
Withdrawn
A request with terminal status left the queue as filed.
That is a record of the filing, not evidence of injection capacity at this location.
Confirm deliverability with LG&E and KU before relying on these figures.
Site Scanner