Tap NBatesville - Leona substation interconnection queue

2 active projects totalling 81.8 MW in the ERCOT queue.

2active projects
81.8active MW
2total filed
Queue IDProjectkVMWResourceStatus
27INR0380 La Mancha Solar SLF 69 40.9 Solar SS Completed, FIS Started, No IA
27INR0381 La Mancha Storage SLF 69 40.9 Battery SS Completed, FIS Started, No IA

Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with ERCOT before relying on these figures.