Bosque, TX interconnection queue
3 active projects totalling 382.9 MW in the ERCOT queue, plus 4 with terminal status (shown greyed).
3active projects
382.9active MW
7total filed
| Queue ID | Project | kV | MW | Resource | Status |
|---|---|---|---|---|---|
| 30INR0005 | Woodland Energy Storage | 345 | 207.6 | Battery | SS Completed, FIS Started, No IA |
| 23INR0295 | Sultan Solar | n/r | 206.1 | Solar | Inactive |
| 24INR0246 | Sultan BESS | n/r | 203.8 | Battery | Inactive |
| 20INR0202 | Rueter Solar | n/r | 200 | Solar | Inactive |
| 25INR0474 | Solheim Solar | 69 | 108.7 | Solar | SS Completed, FIS Completed, No IA |
| 27INR0298 | Symank Solar | 69 | 66.6 | Solar | SS Completed, FIS Started, No IA |
| 20INR0146 | Angus Storage | n/r | 63 | Battery | Inactive |
Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with ERCOT before relying on these figures.