Substation Scout

Bandera, TX interconnection queue

3 active projects totalling 335.8 MW in the ERCOT queue.

3active projects
335.8active MW
3total filed
Queue IDProjectkVMWResourceStatus
26INR0194 Motif BESS II 138 201.1 Battery SS Completed, FIS Started, No IA
23INR0078 Shaw Solar 138 124.7 Solar SS Completed, FIS Completed, IA
24INR0502 Medina City BESS 69 10 Battery In Queue

Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with ERCOT before relying on these figures.