Bandera, TX interconnection queue

3 active projects totalling 335.8 MW in the ERCOT queue.

3active projects
335.8active MW
3total filed
Queue IDProjectkVMWResourceStatus
26INR0194 Motif BESS II 138 201.1 Battery SS Completed, FIS Started, No IA
23INR0078 Shaw Solar 138 124.7 Solar SS Completed, FIS Completed, IA
24INR0502 Medina City BESS 69 10 Battery In Queue

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with ERCOT before relying on these figures.