SPRING HOPE SWITCHING STATION substation interconnection queue

1 active project totaling 50 MW in the Duke Energy queue, plus 1 with terminal status (shown grayed).

2 Duke Energy queue filings name SPRING HOPE SWITCHING STATION as the point of interconnection, all in Nash County, NC.

1active projects
50active MW
2total filed
Queue IDProjectkVMWResourceStatus
565492 Not reported 115 138 Battery Withdrawn
956218 Not reported 115 50 Battery Active

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with Duke Energy before relying on these figures.