GOLDSBORO - KINSTON DUPONT SUB substation interconnection queue
0 active projects
totaling 0 MW in the Duke Energy queue, plus 3 with terminal status (shown grayed).
3 Duke Energy queue filings name GOLDSBORO - KINSTON DUPONT SUB as the point of interconnection, all in NC.
0active projects
0active MW
3total filed
Queue ID
Project
kV
MW
Resource
Status
910089
Not reported
230
80
Solar
Withdrawn
920661
Not reported
230
72
Solar
Withdrawn
910061
Not reported
230
65
Solar
Withdrawn
A request with terminal status left the queue as filed.
That is a record of the filing, not evidence of injection capacity at this location.
Confirm deliverability with Duke Energy before relying on these figures.
Site Scanner