Fort White Substation substation interconnection queue

0 active projects totaling 0 MW in the Duke Energy queue, plus 3 with terminal status (shown grayed).

3 Duke Energy queue filings name Fort White Substation as the point of interconnection, all in FL.

0active projects
0active MW
3total filed
Queue IDProjectkVMWResourceStatus
167 Not reported n/r 74.5 Solar Withdrawn
244 Not reported n/r 74 Solar Withdrawn
245 Not reported n/r 74 Solar Withdrawn

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with Duke Energy before relying on these figures.