Substation Scout

FLORENCE DUPONT - MARION substation interconnection queue

1 active project totaling 63.9 MW in the Duke Energy queue, plus 1 with terminal status (shown grayed).

2 Duke Energy queue filings name FLORENCE DUPONT - MARION as the point of interconnection, all in Marion County, SC.

1active projects
63.9active MW
2total filed
Queue IDProjectkVMWResourceStatus
917501 Not reported 115 74.9 Solar Withdrawn
917739 Not reported 115 63.9 Solar Active

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with Duke Energy before relying on these figures.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first