Brooksville-Bushnell East substation interconnection queue

2 active projects totaling 149.8 MW in the Duke Energy queue.

2 Duke Energy queue filings name Brooksville-Bushnell East as the point of interconnection, all in Hernando County, FL.

2active projects
149.8active MW
2total filed
Queue IDProjectkVMWResourceStatus
319 Not reported n/r 74.9 Solar Suspended
320 Not reported n/r 74.9 Solar Suspended

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with Duke Energy before relying on these figures.