Duke Energy request PP00054

Duke Energy queue ID PP00054

Queue request PP00054 was listed in the Duke Energy interconnection queue at the end of 2025 as a 30 MW project in Darlington County, SC, according to Berkeley Lab’s queue data file. Its status as of December 31, 2025 was “Active”, with a proposed online date of September 15, 2027.

Queue IDPP00054
Project nameNot reported
Status (as published)Active
SubstationNot reported
Point of interconnectionNot reported
CountyDarlington
StateSC
VoltageNot reported
Capacity30 MW
Resource (as published)Other
Resource categoryOther (normalized for filtering)
Proposed online date2027-09-15
Source datasetBerkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025

Same substation and county

Darlington, SC: 40 requests in the Duke Energy queue, 21 active totaling 1,211.4 MW.

Tracked changes

Not tracked. Duke Energy rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.

Additional filed fields

UtilityDuke Energy Progress
Project typeGeneration
Study phase (standardized by Berkeley Lab)In Progress (unknown study)
Study phase (as the queue printed it)Received Provisional Interconnection Request
Queue date2025-10-29

Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.

Fields shown are those in Berkeley Lab’s data file, which standardizes each provider’s queue. The provider’s own queue may carry more fields and newer values. Always confirm against it before relying on any value.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first