Duke Energy request 920663
Duke Energy queue ID 920663
Queue request 920663 was listed in the Duke Energy interconnection queue at the end of 2025 as a 44 MW solar project in Randolph County, NC, according to Berkeley Lab’s queue data file. The filing names ASHEBORO - DPC PLEASANT GARDEN as its point of interconnection. Its status as of December 31, 2025 was “Active”.
| Queue ID | 920663 |
|---|---|
| Project name | Not reported |
| Status (as published) | Active |
| Substation | ASHEBORO - DPC PLEASANT GARDEN |
| Point of interconnection | ASHEBORO - DPC PLEASANT GARDEN 230KV |
| County | Randolph |
| State | NC |
| Voltage | 230 kV |
| Capacity | 44 MW |
| Resource (as published) | Solar |
| Resource category | Solar (normalized for filtering) |
| Proposed online date | Not reported |
| Source dataset | Berkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025 |
Same substation and county
Randolph, NC: 3 requests in the Duke Energy queue, 1 active totaling 44 MW.
Tracked changes
Not tracked. Duke Energy rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.
Additional filed fields
| Utility | Duke Energy Progress |
|---|---|
| Cluster | 2023 Solar + Procurement |
| Interconnection service | Other |
| Project type | Generation |
| Study phase (standardized by Berkeley Lab) | Facility Study |
| Study phase (as the queue printed it) | Facility Study - In Progress |
| Queue date | 2023-09-30 |
Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.
Fields shown are those in Berkeley Lab’s data file, which standardizes each provider’s queue. The provider’s own queue may carry more fields and newer values. Always confirm against it before relying on any value.