Duke Energy request 566170

Duke Energy queue ID 566170

Queue request 566170 was listed in the Duke Energy interconnection queue at the end of 2025 as a 56 MW battery project in Wake County, NC, according to Berkeley Lab’s queue data file. The filing names NEW HILL TAP LINE as its point of interconnection. Its status as of December 31, 2025 was “Active”, with a proposed online date of December 31, 2026.

Queue ID566170
Project nameNot reported
Status (as published)Active
SubstationNEW HILL TAP LINE
Point of interconnectionNEW HILL 230KV TAP LINE
CountyWake
StateNC
Voltage230 kV
Capacity56 MW
Resource (as published)Battery
Resource categoryBattery (normalized for filtering)
Proposed online date2026-12-31
Source datasetBerkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025

Same substation and county

Wake, NC: 15 requests in the Duke Energy queue, 7 active totaling 872 MW.

Tracked changes

Not tracked. Duke Energy rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.

Additional filed fields

UtilityDuke Energy Progress
DeveloperDuke Energy Progress, LLC
Cluster2022 DISIS
Interconnection serviceNRIS/ERIS
Project typeGeneration
Study phase (standardized by Berkeley Lab)IA Executed
Study phase (as the queue printed it)Engineering Design - In Progress
Queue date2022-06-14

Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.

Fields shown are those in Berkeley Lab’s data file, which standardizes each provider’s queue. The provider’s own queue may carry more fields and newer values. Always confirm against it before relying on any value.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first