Duke Energy request 24751

Duke Energy queue ID 24751

Queue request 24751 was listed in the Duke Energy interconnection queue at the end of 2025 as a 14 MW nuclear project in Wake County, NC, according to Berkeley Lab’s queue data file. The filing names Harris Nuclear Plant as its point of interconnection. Its status as of December 31, 2025 was “Operational”.

Queue ID24751
Project nameNot reported
Status (as published)Operational
SubstationHarris Nuclear Plant
Point of interconnectionHarris Nuclear Plant
CountyWake
StateNC
VoltageNot reported
Capacity14 MW
Resource (as published)Nuclear
Resource categoryNuclear (normalized for filtering)
Proposed online dateNot reported
Source datasetBerkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025

Same substation and county

Wake, NC: 15 requests in the Duke Energy queue, 7 active totaling 872 MW.

Tracked changes

Not tracked. Duke Energy rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.

Additional filed fields

UtilityDuke Energy Progress
DeveloperDuke Energy Progress, LLC
Project typeGeneration
Study phase (standardized by Berkeley Lab)IA Executed
Study phase (as the queue printed it)Commercial Operation - Commercial Operation Date Declared
Queue date2017-05-22
Operational date2019-12-11

Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.

Fields shown are those in Berkeley Lab’s data file, which standardizes each provider’s queue. The provider’s own queue may carry more fields and newer values. Always confirm against it before relying on any value.