Duke Energy request 180C

Duke Energy queue ID 180C

Queue request 180C was listed in the Duke Energy interconnection queue at the end of 2025 as a 74.5 MW solar project, according to Berkeley Lab’s queue data file. The filing names Highbanks Substation as its point of interconnection. Its status as of December 31, 2025 was “Operational”, with a proposed online date of December 31, 2018.

Queue ID180C
Project nameNot reported
Status (as published)Operational
SubstationHighbanks Substation
Point of interconnectionHighbanks Substation 115 kV
CountyNot reported
StateNot reported
Voltage115 kV
Capacity74.5 MW
Resource (as published)Solar
Resource categorySolar (normalized for filtering)
Proposed online date2018-12-31
Source datasetBerkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025

Tracked changes

Not tracked. Duke Energy rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.

Additional filed fields

UtilityDuke Energy Florida
DeveloperDuke Energy Florida, LLC
Interconnection serviceNRIS
Project typeGeneration
Study phase (standardized by Berkeley Lab)IA Executed
Queue date2017-04-10

Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.

Fields shown are those in Berkeley Lab’s data file, which standardizes each provider’s queue. The provider’s own queue may carry more fields and newer values. Always confirm against it before relying on any value.