Duke Energy request 180C
Duke Energy queue ID 180C
Queue request 180C was listed in the Duke Energy interconnection queue at the end of 2025 as a 74.5 MW solar project, according to Berkeley Lab’s queue data file. The filing names Highbanks Substation as its point of interconnection. Its status as of December 31, 2025 was “Operational”, with a proposed online date of December 31, 2018.
| Queue ID | 180C |
|---|---|
| Project name | Not reported |
| Status (as published) | Operational |
| Substation | Highbanks Substation |
| Point of interconnection | Highbanks Substation 115 kV |
| County | Not reported |
| State | Not reported |
| Voltage | 115 kV |
| Capacity | 74.5 MW |
| Resource (as published) | Solar |
| Resource category | Solar (normalized for filtering) |
| Proposed online date | 2018-12-31 |
| Source dataset | Berkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025 |
Tracked changes
Not tracked. Duke Energy rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.
Additional filed fields
| Utility | Duke Energy Florida |
|---|---|
| Developer | Duke Energy Florida, LLC |
| Interconnection service | NRIS |
| Project type | Generation |
| Study phase (standardized by Berkeley Lab) | IA Executed |
| Queue date | 2017-04-10 |
Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.