Duke Energy request 17114
Duke Energy queue ID 17114
Queue request 17114 was listed in the Duke Energy interconnection queue at the end of 2025 as a 500 MW gas project, according to Berkeley Lab’s queue data file. The filing names Dixon School Road Switching Station as its point of interconnection. Its status as of December 31, 2025 was “Operational”.
| Queue ID | 17114 |
|---|---|
| Project name | Not reported |
| Status (as published) | Operational |
| Substation | Dixon School Road Switching Station |
| Point of interconnection | Dixon School Road Switching Station |
| County | Not reported |
| State | Not reported |
| Voltage | Not reported |
| Capacity | 500 MW |
| Resource (as published) | Gas |
| Resource category | Gas (normalized for filtering) |
| Proposed online date | Not reported |
| Source dataset | Berkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025 |
Tracked changes
Not tracked. Duke Energy rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.
Additional filed fields
| Developer | NTE Carolinas, LLC |
|---|---|
| Interconnection service | NRIS |
| Study phase (standardized by Berkeley Lab) | IA Executed |
| Study phase (as the queue printed it) | Commercial Operation - Commercial Operation Date Declared |
| Queue date | 2013-12-31 |
| Operational date | 2018-02-07 |
Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.
Fields shown are those in Berkeley Lab’s data file, which standardizes each provider’s queue. The provider’s own queue may carry more fields and newer values. Always confirm against it before relying on any value.