Queue request 16227 was listed in the Duke Energy interconnection queue at the end of 2025 as a 2 MW solar project in Darlington County, SC, according to Berkeley Lab’s queue data file. The filing names HARTSVILLE SEGARS MILL as its point of interconnection. Its status as of December 31, 2025 was “Operational”, with a proposed online date of December 15, 2023.

Queue ID16227
Project nameNot reported
Status (as published)Operational
SubstationHARTSVILLE SEGARS MILL
Point of interconnectionHARTSVILLE SEGARS MILL 230KV
CountyDarlington
StateSC
Voltage230 kV
Capacity2 MW
Resource (as published)Solar
Resource categorySolar (normalized for filtering)
Proposed online date2023-12-15
Source datasetBerkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025

Same substation and county

Darlington, SC: 40 requests in the Duke Energy queue, 21 active totaling 1,211.4 MW.

Tracked changes

Not tracked. Duke Energy rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.

Additional filed fields

UtilityDuke Energy Progress
ClusterTransitional Cluster Study
Interconnection serviceOther
Project typeGeneration
Study phase (standardized by Berkeley Lab)IA Executed
Study phase (as the queue printed it)Commercial Operation - Power Generation in Progress
Queue date2017-08-03
Operational date2023-12-04

Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.

Fields shown are those in Berkeley Lab’s data file, which standardizes each provider’s queue. The provider’s own queue may carry more fields and newer values. Always confirm against it before relying on any value.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first