Chesterfield, SC interconnection queue

6 active projects totaling 400.7 MW in the Duke Energy queue, plus 11 with terminal status (shown grayed).

6active projects
400.7active MW
17total filed
Queue IDProjectkVMWResourceStatus
956283 Not reported 230 110 Solar Withdrawn
962635 Not reported 230 80 Solar Active
566488 Not reported 230 74.9 Solar Active
915761 Not reported 115 74.9 Solar Withdrawn
918047 Not reported n/r 74.9 Solar Withdrawn
956721 Not reported 115 74.9 Solar Withdrawn
977873 Not reported 115 74.9 Solar Active
PP00003 Not reported n/r 74.9 Solar Active
16321 Not reported 115 70 Solar Withdrawn
569996 Not reported 230 66 Solar Withdrawn
956321 Not reported 230 60 Battery Withdrawn
5649 Not reported 230 50 Solar Withdrawn
564942 Not reported 115 48 Solar Withdrawn
961214 Not reported 115 48 Solar Active
PP00052 Not reported n/r 48 Other Active
957082 Not reported 115 30 Solar Withdrawn
30360 Not reported 230 20 Solar Withdrawn

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with Duke Energy before relying on these figures.