Substation Scout

Chester, SC interconnection queue

2 active projects totaling 89.7 MW in the Duke Energy queue, plus 10 with terminal status (shown grayed).

2active projects
89.7active MW
12total filed
Queue IDProjectkVMWResourceStatus
66052 Not reported 100 74.5 Solar Withdrawn
48968 Not reported n/r 69.8 Solar Active
963467 Not reported 100 68 Solar Withdrawn
920667 Not reported n/r 64 Solar Withdrawn
920197 Not reported n/r 44 Solar Withdrawn
962805 Not reported 100 44 Solar Withdrawn
16298 Not reported n/r 39 Solar Withdrawn
918031 Not reported n/r 30 Solar Withdrawn
962985 Not reported n/r 20 Solar Withdrawn
977884 Not reported 100 19.9 Solar Active
15376 Not reported n/r 15 Solar Withdrawn
957241 Not reported n/r 6 Solar Withdrawn

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with Duke Energy before relying on these figures.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →