Double Tap Parker () - Benbrook ( and ) DCKT substation interconnection queue
2 active projects totalling 1,500 MW in the ERCOT queue.
2active projects
1,500active MW
2total filed
| Queue ID | Project | kV | MW | Resource | Status |
|---|---|---|---|---|---|
| 27INR0571 | Nabla Energy Storage I | 345 | 750 | Battery | SS Completed, FIS Started, No IA |
| 28INR0466 | Nabla Energy Storage II | 345 | 750 | Battery | SS Completed, FIS Started, No IA |
Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with ERCOT before relying on these figures.