East Elkhart Bypass - Weeds Lake 345 kV

PJM queue ID C01-1203

Queue IDC01-1203
Project nameEast Elkhart Bypass - Weeds Lake 345 kV
Status (as published)Active
SubstationEast Elkhart Bypass - Weeds Lake
Point of interconnectionEast Elkhart Bypass - Weeds Lake 345 kV
CountyCass
StateMI
Voltage345 kV
Capacity184 MW
Resource (as published)Solar
Resource categorySolar (normalised for filtering)
Target commercial operation2030-12-31
Source datasetcycle

Additional filed fields

DeveloperBair Lake Power, LLC
Transmission OwnerAEP
Project TypeGeneration Interconnection
CycleC01
StagePhase 1
Mw Energy200.0
Mw Capacity184.0
Mfo200.0
Submitted Date4/27/2026
Last Updated6/25/2026

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.